An extremely muddy 14MW site in Evesham, UK

 

2015-03-01 12.09.27

Completed and connected in 6 weeks in February and March 2015 this site was extremely difficult. We had to connect by March 21st but the material deliveries were delayed in ports by heavy storms. And the mud did help either. Sometimes even walking from one side of the field to the other was a problem. To meet the deadline, we had 120 people on site working 7 days a week.